State of Connecticut EDS Contract Compliance Report
Appendix A-2
Department of Social Services/Electronic Data Systems, Inc. Timeline
Workplan Event Timeline
| Date | Event |
|---|---|
| 1/1/1994 | EDS submits the Detailed Workplan per contract. |
| 1/26/1994 | DSS notifies EDS of its outright disapproval of the Detailed Workplan. |
| 2/4/1994 | EDS resubmits. |
| 2/23/1994 | DSS disapproves again |
| 3/4/1994 | EDS indicates it cannot comply with the contract by providing a Detailed Workplan. Continued research into life cycle methodology was the given reason. |
| 3/17/1994 | EDS presents an overview of its "Systems Life Cycle * Rapid Iterative Systems Engineering" (SLC*RISE). |
| 3/23/1994 | EDS submits a new Detailed Workplan. |
| 6/3/1994 | EDS submits its "Final Required Specifications Document (RSD)" |
| 6/21/1994 | DSS unconditionally approves the RSD. |
| 7/11/1994 | EDS resubmits third "Final ConnPACE RSD." |
| 7/13/1994 | DSS unconditionally approves the ConnPACE RSD. |
| 12/30/1994 | Required a fully operational CT AIM. |
| 2/7/1995 | Maximus indicates EDS has not delivered an updated Detailed Workplan since 12/8/1994 and that "project slippage is quite evident." |
| 3/2/1995 | EDS submits a new Detailed Workplan. |
| 4/12/1995 | DSS memo to EDS noted numerous discrepancies between the accepted planned start dates of the 9/1994 Detailed Workplan and the 3/8/1995 revised Detailed Workplan. |
| 10/23/1995 | EDS submits a revised Project Workplan to DSS. This work plan uses a May 1, 1996 implementation date. |
| 12/5/1995 | DSS indicates its "outright disapproval" of the revised workplan. |
| 8/1/1996 | DSS requests a revised work plan by 8/6/1996. |
| 8/6/1996 | EDS submits a plan which is immediately rejected because it merely presented an overview of a new, proposed plan. |
| 11/12/1996 | EDS submits a revised AIM work plan that targets a 7/1/1997 implementation date. |